In Western Australia, dust control and monitoring on construction sites is regulated through local government approvals, the Environmental Protection Act 1986 and work health and safety law.
Regulators expect you to assess dust risk before work starts, keep airborne dust within the boundary, respond to complaints quickly and, on higher-risk sites, back it up with data.
Who regulates construction dust in WA?
Three regulators are involved, each looking at a different aspect of dust risk:
- Local government regulates dust from development and building sites. Councils can make a dust management plan a condition of approval, investigate complaints through their environmental health officers and take enforcement action. Some have their own policies, such as the City of Wanneroo’s local planning policy on earthworks and sand drift.
- DWER (the Department of Water and Environmental Regulation) administers the Environmental Protection Act 1986, under which causing pollution is an offence. It also publishes the state’s dust guideline, regulates licensed (prescribed) premises and acts alongside local government.
- WorkSafe WA regulates worker exposure under the Work Health and Safety (General) Regulations 2022. The workplace exposure standard for respirable crystalline silica is 0.05 mg/m³ averaged over an eight-hour shift.
At a federal level, the National Environment Protection (Ambient Air Quality) Measure (NEPM) sets air quality standards that governments report against. It doesn’t apply directly to a construction site, but its values, such as 50 µg/m³ for PM10 averaged over 24 hours, are the criteria the dust guideline uses for monitoring at the site boundary.
What the WA dust guideline expects
The main reference for site managers is A guideline for managing the impacts of dust and associated contaminants from land development sites, contaminated sites remediation and other related activities (2011), published by DWER. It asks you to score the site on soil type, topography, disturbed area, type of work, distance to neighbours and wind exposure, which gives a risk class from 1 to 4.
| Class | Risk | What is expected |
|---|---|---|
| Class 1 | Negligible | Standard site practice |
| Class 2 | Low | Contingency plan to the local government, water carts and wind fencing allowed for, a complaints system and a site notice with contact details |
| Class 3 | Medium | Wind fencing available within an hour, water carts working within 18 hours, surface stabilisation within 48 hours, on-site and boundary monitoring, exceedances reported |
| Class 4 | High | Neighbours notified 48 hours before work, fencing up before ground is disturbed, water carts working immediately, monitoring as for Class 3 |
Works between 1 October and 31 March move up a class where neighbours are within 100 metres. That window covers Perth’s dry season and strongest afternoon sea breezes. On Class 3 and 4 sites, boundary exceedances must be reported to the regulator within 24 hours, and on every classified site complaints must be logged, investigated and answered.
Dust suppression and control measures for WA conditions
Much of the Swan Coastal Plain is sand and those exposed grounds lift as soon as the wind picks up.
The most effect control measures here are:
- Staging: clear and strip in stages so the disturbed area stays as small as practical.
- Water: utilise water carts and sprinklers on haul roads, stockpiles and work faces, sized for the disturbed area and mobilised before the wind rises.
- Surface stabilisation: polymer binders, hydromulch or early revegetation on areas that won’t be worked for a while.
- Wind fencing and hoarding: shade cloth on boundary fencing and solid hoarding next to neighbours.
- Traffic: speed limits on unsealed roads, stabilised entries and rumble grids or wheel washes to keep material off public roads.
- Activity planning: stop or scale back dusty activities when wind or dust triggers are reached.
- Silica tasks: wet cutting and on-tool extraction when cutting, grinding or drilling concrete or stone, with respiratory protection where fine particles remain.
What you need to monitor on a construction site
Hard data shows if your controls are working and gives you evidence should a neighbour or regulator question them. A typical program covers:
| Parameter | Method | What it tells you |
|---|---|---|
| Visible dust | Daily inspections and a dust log | Whether dust is leaving the site, and what was done about it |
| Wind speed and direction | On-site weather station | When to step up controls or stop work, and where dust is travelling |
| PM10 and PM2.5 | Real-time monitors at the boundary | Short-term concentrations against trigger levels and the guideline criteria |
| Dust deposition | Dust deposition gauges | Longer-term fallout on neighbouring properties, reported monthly |
| Worker exposure | Personal sampling for respirable dust and silica | Compliance with workplace exposure standards |
| Complaints | Complaints register | What neighbours are noticing, and how quickly you responded |
It’s important to set trigger levels before earthworks begin, each with a defined response, such as more water at the first trigger and stopping dusty activities at the second. Also look to collect background data first (the guideline suggests about four weeks for projects of up to six months) and aim for at least 90% data capture each month.
Common dust control mistakes
- Writing a dust management plan for approval only and not actually using it on site.
- Starting measurement after the first complaint, with no baseline to compare against.
- Running real-time monitors with no trigger levels, or nobody assigned to respond to alerts.
- Relying on water alone through summer, or under-sizing water carts for the disturbed area.
- Treating boundary monitoring as proof of worker safety. Boundary monitors measure what leaves the site, while worker exposure needs personal sampling for silica and respirable dust.
- Letting data gaps build up through flat batteries or failed modems, which weakens the record when you need it.
How we support dust control on WA construction sites
We design, install and run tailored dust monitoring programs for construction, civil and land development projects across Western Australia.
Our stations are built in-house and solar powered, and use beta attenuation monitors (BAMs), TEOMs and dust deposition gauges depending on the project. They send SMS and email alerts when trigger levels are reached, and you can view results through our remote data portal.
We can add weather stations, noise loggers and vibration loggers to the same system and our occupational hygienists handle worker exposure sampling for silica and respirable dust. We mobilise quickly across WA and provide reporting you can hand to your council, DWER or your client.